X

Thank you for sharing!

Your article was successfully shared with the contacts you provided.

DECISION AND ORDER I. INTRODUCTION Pending before the Court is a motion for summary judgment filed by defendant Argonaut Insurance Company (“Defendant”). (Dkt. 25). Because material issues of fact prevent resolution of this case as a matter of law at this pre-answer stage of the proceedings, the motion is denied. II. BACKGROUND This matter arises from a construction project in Dover, New York, known as the Cricket Valley Energy Administration and MCE Building Project (“the Project”). (See Dkt. 1-1 at 9, 4; Dkt. 25-12 at 1). Plaintiff LeChase Construction Services, LLC (“Plaintiff”) performed work on the Project. (Dkt. 25-12 at 1; Dkt. 26-19 at 1). On June 8, 2017, Plaintiff entered into a subcontract with United Structures of America, Inc. (“USA”) to provide structural steel design and fabrication for the Project. (Dkt. 25-12 at 2; Dkt. 26-19 at 2). USA’s original contract amount with Plaintiff was $3,874,383. (Dkt. 25-12 at 3; Dkt. 26-19 at 3). USA as principal executed a Supply Bond (“the Bond”) with Defendant as surety in the amount of $3,874,383. (Dkt. 25-12 at 4; Dkt. 26-19 at 4; see Dkt. 25-9). The Bond was issued to and accepted by Plaintiff, as obligee. (Dkt. 25-12 at 5; Dkt. 26-19 at 5). The Bond states, in relevant part, as follows: [A]ny suit by [Plaintiff] under this bond must be instituted before…the earlier of: (a) the expiration of one year from the date [USA] was obligated under the Material Contract to deliver the materials to [Plaintiff], or (b) the expiration of one year from the date any other default by [USA] under the Material Contract. (Dkt. 25-9 at 1 (emphasis added)). Plaintiff filed its complaint on July 20, 2020, in New York State Supreme Court, Monroe County. (Dkt. 1-1 at 11). The crux of the dispute on the pending motion is whether USA defaulted prior to July 20, 2019, because if so and if no exception applies, the claim would be untimely. On September 18, 2019, Plaintiff issued Purchase Change Order No. 18 (“Change Order 18″) that reduced USA’s contract balance by $144,000, which according to Plaintiff accounted for the removal of site supervision from USA’s scope of work and still resulted in a positive value on USA’s subcontract. (Dkt. 25-12 at 8; Dkt. 26-19 at 8). The description on Change Order 18 stated: “Additional LCS Costs due to USA Breach of Contract. Costs Include Added LeChase General Conditions to manage USA abandonment of the work, additional fabrication issues that have been discovered.” (Dkt. 25-10 at 1 (emphasis added)). A spreadsheet attached to Change Order 18 details additional costs incurred by Plaintiff commencing on July 2, 2018. (Id. at 2; see also id. at 9). Defendant contends that Plaintiff submitted a formal claim on the Bond on November 1, 2019 (Dkt. 25-12 at 13), but Plaintiff denies that this correspondence was a formal claim — instead arguing that it submitted costs to Defendant on that date in the amount of $431,421.68 relating to costs it had incurred as a result of USA’s default, and that it first notified Defendant of issues relating to USA’s performance on the Project on September 5, 2019 (Dkt. 26-19 at 13). Plaintiff contends that its claim on the Bond is “limited to USA’s default for failing to indemnify and make [Plaintiff] whole for the costs outlined in the letter dated October 28, 2019.” (Id. at 14). By letter dated February 12, 2020, Plaintiff wrote to Defendant outlining that its total claim against the Bond was $2,232,212.68, plus interest and attorneys’ fees. (Dkt. 25-11). In that letter, Plaintiff states, among other things, that its costs underlying the Bond are tied, in part, to Change Order 18, which “contains certain additional labor costs attributable to the significant increase in the amount of time required by [Plaintiff's] field management staff to manage fabrication errors, incomplete or inaccurate deliveries, and other problems with orders, materials, and related safety issues caused by USA.” (Id. at 1). Plaintiff further states that these issues and its costs “were exacerbated by USA’s refusal to come to the jobsite and manage these issues itself.” (Id.). This necessitated, according to Plaintiff, its assignment of an additional superintendent to the Project (whose spreadsheet of time is attached to Change Order 18, reflecting the time commencing on July 2, 2018). (Id. at 1-2). Defendant contends that it denied Plaintiff’s claim on the Bond, in part, on the basis that the claim was untimely because the action was not filed within one year of USA’s default. (See Dkt. 25-13 at 7). After commencement of this action, the case was removed to this Court on October 30, 2020, on the basis for diversity jurisdiction. (Dkt. 1).1 After removal, the Court granted Plaintiff’s motion to remand and denied Defendant’s summary judgment motion as moot. (Dkt. 15). The Second Circuit Court of Appeals vacated the Court’s remand order and sent the case back for further proceedings. (Dkt. 19). After conferring with the parties, a briefing schedule was set for the filing of Defendant’s renewed motion for summary judgment. (Dkt. 22; Dkt. 24). Defendant filed its summary judgment motion on June 30, 2023. (Dkt. 25). Plaintiff responded in opposition on July 28, 2023. (Dkt. 26). Defendant filed a reply memorandum in further support of its motion on August 18, 2023. (Dkt. 27). Oral argument was held before the undersigned on November 28, 2023, at which time the Court reserved decision. (Dkt. 31). After oral argument, Plaintiff submitted without leave further papers in opposition to the motion for summary judgment. (Dkt. 32). Defendant filed a letter objecting to the untimely filing (Dkt. 34), and Plaintiff submitted a response (Dkt. 35). Because Plaintiff failed to request leave before making its additional submissions, and even now only seeks leave as an afterthought in a letter filed in response to Defendant’s objections, see W.D.N.Y. Loc. R. Civ. P. 6(a)(6) (“Absent permission of the Judge hearing the motion, sur-reply papers are not permitted.”), the Court will not consider the post-argument submissions. III. DISCUSSION Rule 56 of the Federal Rules of Civil Procedure provides that summary judgment should be granted if the moving party establishes “that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). The Court should grant summary judgment if, after considering the evidence in the light most favorable to the nonmoving party, the court finds that no rational jury could find in favor of that party. Scott v. Harris, 550 U.S. 372, 380 (2007) (citing Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 586-87 (1986)). Once the moving party has met its burden, the opposing party “must do more than simply show that there is some metaphysical doubt as to the material facts.…[T]he nonmoving party must come forward with specific facts showing that there is a genuine issue for trial.” Caldarola v. Calabrese, 298 F.3d 156, 160 (2d Cir. 2002) (quoting Matsushita Elec., 475 U.S. at 586-87). “[T]he mere existence of some alleged factual dispute between the parties will not defeat an otherwise properly supported motion for summary judgment….” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-48 (1986). The obligations of a surety such as Defendant “are limited to those it undertakes in its bond and that the bond attaches to the principal contract and must be construed in conjunction therewith….” Annuity, Pension, Welfare & Appretinceship Skill Improvement & Safety Funds of Intl Union of Operating Engineers v. Colonial Sur. Co., No. 11-CV-00178 NSR, 2014 WL 4493803, at *3 (S.D.N.Y. Sept. 11, 2014) (quoting Varlotta Constr. Corp v. Sette-Juliano Constr. Corp., 234 A.D.2d 183, 183 (1st Dep’t 1996)).2 “Courts ‘look to standard principles of contract interpretation to determine the rights and obligations of a surety under a bond.’” Nobel Ins. Co. v. City of New York, No. 00-CV-1328 KMK, 2006 WL 2848121, at *9 (S.D.N.Y. Sept. 29, 2006) (quoting U.S. Fid. & Guar. Co. v. Braspetro Oil Servs. Co., 369 F.3d 34, 51 (2d Cir. 2004)). “New York courts construe bonds like any other contract in order to determine the parties’ rights and obligations thereunder.…However, to the extent that provisions of a surety bond issued by a compensated surety are ambiguous, courts construe them against the surety.” Shawnlee Const., LLC v. J.K. Scanlan Co., 42 F. Supp. 3d 561, 570 (S.D.N.Y. 2014). See U.S. Fid. & Guar., 369 F.3d at 74 (“And, as we have noted in previous cases, ‘[u]nder New York law, it is well established that “[a] compensated, corporate surety…is not a favorite of the law and its contract of suretyship will be construed in a manner most favorable to [the] claimant.”‘” (quoting Cam-Ful Indus., Inc. v. Fid. & Deposit Co. of Maryland, 922 F.2d 156, 163 (2d Cir. 1991))). The record here establishes by Plaintiff’s own admissions that more than one year prior to commencement of this action, it viewed USA to be in breach of contract. That fact cannot be reasonably disputed. (See, e.g., Dkt. 25-10 at 1 (Change Order 18 wherein Plaintiff states that USA breached the contract)). But the Bond requires the timely commencement of an action within one year of a “default” by USA, not necessarily a “breach.” The term “default” is not defined in the Bond or the underlying contractual documents. Cf. E & T Skyline Constr., LLC v. Talisman Cas. Ins. Co., LLC, No. 19-CV-8069 (JSR), 2023 WL 7297212, at *7 (S.D.N.Y. Nov. 6, 2023) (“Bond Agreement defined…default to include a failure ‘to perform and complete or comply with the other material terms of the’ subcontract.”). As the court recognized in Elm Haven Const. Ltd. P’ship v. Neri Const., LLC, 281 F. Supp. 2d 406, 412 (D. Conn. 2003), aff’d, 376 F.3d 96 (2d Cir. 2004), the word “default” has a distinct meaning in the context of construction suretyship law, and “[n]ot every breach of a construction contract constitutes a default….” (quoting L & A Contracting Co. v. S. Concrete Servs., Inc., 17 F.3d 106, 110 (5th Cir. 1994)).3 The Elm Haven court went on to explain: “A legal default requires a material breach or series of material breaches such that the obligee is justified in terminating the contract.…Thus, there is a distinction in the concepts of ‘breach’ and ‘default’ that is to be recognized in construction suretyship law.” Id. at 412-13 (citations omitted). In view of this, summary judgment must be denied based on the present record. In other words, while the record establishes that USA breached the contract more than a year prior to Plaintiff’s commencement of this action, it cannot be said that there is no dispute that USA was in default under the terms of the contract at that point. Especially where the term default is not defined in the Bond and any ambiguous terms are construed against Defendant as the surety, it would be inappropriate to resolve the case as a matter of law at this stage of the litigation. Because of that, the Court need not and does not reach the other issues raised by the parties that would only be relevant in the event it was undisputed that a default occurred by USA more than one year prior to commencement of the action. IV. CONCLUSION For the foregoing reasons, Defendant’s motion for summary judgment is denied. (Dkt. 25). SO ORDERED. Dated: February 12, 2024

 
Reprints & Licensing
Mentioned in a Law.com story?

License our industry-leading legal content to extend your thought leadership and build your brand.

More From ALM

With this subscription you will receive unlimited access to high quality, online, on-demand premium content from well-respected faculty in the legal industry. This is perfect for attorneys licensed in multiple jurisdictions or for attorneys that have fulfilled their CLE requirement but need to access resourceful information for their practice areas.
View Now
Our Team Account subscription service is for legal teams of four or more attorneys. Each attorney is granted unlimited access to high quality, on-demand premium content from well-respected faculty in the legal industry along with administrative access to easily manage CLE for the entire team.
View Now
Gain access to some of the most knowledgeable and experienced attorneys with our 2 bundle options! Our Compliance bundles are curated by CLE Counselors and include current legal topics and challenges within the industry. Our second option allows you to build your bundle and strategically select the content that pertains to your needs. Both options are priced the same.
View Now
September 05, 2024
New York, NY

The New York Law Journal honors attorneys and judges who have made a remarkable difference in the legal profession in New York.


Learn More
May 15, 2024
Philadelphia, PA

The Legal Intelligencer honors lawyers leaving a mark on the legal community in Pennsylvania and Delaware.


Learn More
May 16, 2024
Dallas, TX

Consulting Magazine recognizes leaders in technology across three categories Leadership, Client Service and Innovation.


Learn More

We are seeking an associate to join our Employee Benefits practice. Candidates should have three to six years of employee benefits experienc...


Apply Now ›

Associate attorney position at NJ Immigration Law firm: Leschak & Associates, LLC, based in Freehold, NJ, is looking for a full time ass...


Apply Now ›

Duane Morris LLP has an immediate opening for a senior level, highly motivated litigation associate to join its dynamic and growing Employme...


Apply Now ›
04/29/2024
The National Law Journal

Professional Announcement


View Announcement ›
04/15/2024
Connecticut Law Tribune

MELICK & PORTER, LLP PROMOTES CONNECTICUT PARTNERS HOLLY ROGERS, STEVEN BANKS, and ALEXANDER AHRENS


View Announcement ›
04/11/2024
New Jersey Law Journal

Professional Announcement


View Announcement ›