JUSTICE DEVINE delivered the opinion of the Court. Justice Lehrmann did not participate in the decision. The Local Government Contract Claims Act waives immunity from suit for breach of contract when a local governmental entity enters into certain written contracts, including those âstating the essential terms of the agreement for providing . . . services toâ that entity.[1] In this breach-of-contract suit to enforce alleged vested rights in sewer-flow capacity, the issue on appeal is whether a written instrument documenting the terms and conditions for a municipal water system to provide sewer service to and guarantee capacity for a developerâs planned subdivisions formed a contract for which the Act waives immunity. Central to the dispute are the terms of an option for the developer to participate in and fund the construction of off-site oversized infrastructure, which the system would then own to ensure sufficient capacity for the new developments. The court of appeals concluded the Act did not apply, and therefore did not waive immunity, because there was no agreement for providing services to the system; that is, the system had no contractual right to receive any services and would not have âany legal recourseâ if the developer âunilaterally decided not to proceed.â[2] We disagree and hold that the Act waived the systemâs immunity from suit because the developer adduced evidence that (1) a contract formed when the developer decided to and did participate in the off-site oversizing project, (2) the written contract states the essential terms of an agreement for the developer to participate in that project, and (3) the agreement was for providing a service to the system that was neither indirect nor attenuated. We therefore reverse the court of appealsâ judgment and remand the case to the trial court for further proceedings. I. Background In 2003, Campbelton Road, Ltd.(the Developer)[3] and San Antonio Water System (SAWS) signed an Outer Service Area Sewer Service Contract.[4] The Contract identifies SAWS as the City of San Antonioâs water, wastewater, and water re-use agency and the City as the responsible government agency for constructing, operating, and maintaining the sewerage system in a defined area. Outside city limits but within the service area,[5] the Developer owned a 585-acre tract of land, which it planned to develop into two residential subdivisions with sewer service. To this end, the Contract recites that SAWSâs collection and treatment of the tractâs wastewater are in the public interest and that the parties wished to document the agreementâs terms regarding such services.[6] The Contract states that it would âremain in full force and effectâ for ten years. Among other terms and conditions, the Developer would submit a project master plan, engineering report, and water plan and comply with design, construction, and permitting procedures for sewer-infrastructure development. Off-site systems would be considered temporary facilities until SAWSâs director of infrastructure development determined they were âan integral part of [SAWS]âs regional sewerage system.â After SAWS accepted the infrastructure, the Developer would convey its âright, title and interestâ to it, and SAWS âshall thereafter own, operate, and maintain said systemsâ with âthe right to connect wastewater flows from other developments.â[7] Before the development can be connected to SAWSâs sewer service, the Contract requires the Developer to pay sewer-collection and wastewater-treatment components of an impact fee,[8] to be calculated in accordance with the fees in effect at the time of plat recordation.[9] Impact fees are means by which a governmental entity may recoup the costs of necessary capital improvements to serve a new development.[10] Once the Developer satisfied the initial payment obligation, SAWS would then charge monthly fees for treatment and disposal of the tractâs flows. The Contract sets the maximum average daily flow from the tract at 450,000 gallons per day, which equals 1,500 equivalent dwelling units (EDUs), a standardized measure based on wastewater use attributable to a single-family residence.[11] Before plat approval, however, SAWSâs director would âmake a final determinationâ of the maximum allowable flow capacity but âmay not reduce the capacityâ below 1,500 EDUs if the Developer materially complied with its contractual obligations. And by paying âthe collection and/or treatmentâ impact fees, the Developer would acquire vested rights to the capacity. On the other hand, if the Developer had not âcompleted construction of the off-site line and/or not paid all impact fees required herein [in] order to earn vested rights and collection component creditsâ before the ten-year term ended, the parties agreed in the Contract that SAWS would continue to accept flows from the tract, recognize the Developerâs right to any unused capacity, and apply any impact-fee credits to which the Developer was entitled. At the time the parties signed the Contract, SAWS was planning a wastewater consolidation system for the Southside Independent School District to serve the schools and surrounding developments. Given the potential wastewater flows from the Developerâs nearby tract, the Contract states that SAWS expected to include in its construction bid an alternative oversize option for the sewer infrastructureâlift stations and force mains[12]âat two schools to increase SAWSâs flow capacity (the Southside project). The Developer âmust decide if [it] wish[es] to participateâ and be responsible for the share of the costs to build the oversize option. But it had to decide âwithin 2 weeks of bid openingâ without âinterrupt[ing] the project schedule,â pay its share âto SAWS prior to contract award,â and be responsible for costs related to any relevant change orders. If the Developer did not elect to participate, it would be responsible for only the engineering fees related to preparing the oversize option and, presumably, SAWS would bid the construction of only the base model. In exchange for its participation, the Developer would be eligible under the Contract for collection impact-fee credits for its cost share.[13] These credits âattach to the real estateâ and could be used to satisfy some, or all, of the collection component of assessed impact fees,[14] depending on whether the credits exceeded the assessed amount. The Contract states that the collection component of the impact fees âmay currently be estimated . . . at $366.00 Per EDUâ (in other words, $549,000 for 1,500 EDUs). SAWS also would be obligated to supply sewer service âupon completion of the oversized projectâ and âacceptance of an impact feeâ without âthe construction of a specific facility to provide such sewer service, other [than] the [Southside] Project.â But because the Southside project would not connect to the subdivisions, the Developer would remain responsible for the costs, easements, permitting, and construction of connecting infrastructure. The record indicates that the Developer decided to participate in the Southside project and paid its share of the costsâaccording to the Developer, it âspent millions.â But the Developer acknowledged in its pleadings that it did not develop the subdivisions within the Contractâs ten-year term. Instead, it waited until 2019âsix years after the term endedâto âcommence developmentâ and reach out to SAWS regarding the 1,500-EDU capacity. Noting that the capacity had been set aside for ten years,[15] SAWS responded that it now had no unused capacity. SAWS offered to execute a new utility-service agreement with the Developer to allocate capacity for the subdivisions but would require either further upgrades to the Southside project or the construction of an alternative lift structure for connection. SAWS estimated that to supply 1,500 EDUs, the necessary upgrades would cost $7.7 million. After an unsuccessful administrative appeal,[16] the Developer sued the City by and through SAWS for breach of contract, seeking both money damages and specific performance to supply the Developer with a capacity of 1,500 EDUs.[17] The Developer alleged that by participating in the Southside project and earning collection credits, it had acquired a vested right to the capacity and that SAWS breached the Contract by allocating the capacity to others.[18] In response, SAWS asserted its governmental immunity in a plea to the jurisdiction and then took an interlocutory appeal from the trial courtâs order denying the plea.[19] The court of appeals reversed, concluding that the Act did not waive SAWSâs governmental immunity because the Contract was not an agreement for providing goods or services to SAWS.[20] Relying primarily on our opinion in Lubbock County Water Control & Improvement District v. Church & Akin, L.L.C.,[21] the court of appeals held: (1) the Contractâs purpose was for the Developer to receive services from SAWS; (2) SAWS, on the other hand, had no right to receive any services under the Contract and no legal recourse if the Developer âunilaterally decided not to proceed with the developments and not complete any provisions of the contractâ; (3) the Contract does not require SAWS to purchase any services from the Developer; (4) the purpose of the Southside project was not âfor the direct benefit of SAWSâ but for the benefit of the Developerâs subdivisions; and (5) any benefit SAWS received was indirect and not part of the agreementâs essential terms.[22] The Developer petitioned this Court for review, which we granted. II. Discussion The Developer does not dispute that SAWS is a governmental entity entitled to immunity. The jurisdictional question here, one we review de novo,[23] is whether the Developer satisfied its burden to establish, or at least raise a fact issue on, a waiver of that immunity.[24] The Developer relies on the waiver of immunity in Section 271.152 of the Local Government Code. Although the statute unquestionably waives immunity, the question is whether the Developerâs breach-of-contract suit falls within its ambit. In determining the scope of a statutory waiver of immunity, we apply traditional principles of statutory interpretation to ascertain and effectuate legislative intent as manifested in the enacted language.[25] To the extent the analysis also requires interpreting the partiesâ contract, our primary objective is similarly to ascertain and give effect to their âtrue intentions as expressed in the language they chose.â[26] A. The Local Government Contract Claims Act We begin with a brief overview of governmental immunity and the Act. Before 2005, âgovernmental immunity shielded a local government from enforcement of its contract obligations.â[27] Justified on âpolitical, pecuniary, and pragmaticâ grounds,[28] the doctrine protects the public from the costs and consequences of their governmentâs improvident actions and allows the Legislature to be the arbiter of when tax resources should be shifted âaway from their intended purposes toward defending lawsuits.â[29] In the contract context, the doctrine âensures that current policymakers are neither bound by, nor held accountable for, policies underlying their predecessorsâ long-term contracts.â[30] As a common-law doctrine, the judiciary determines governmental immunityâs initial applicability.[31] But it is the Legislatureâs province to balance the policy considerations in determining when to waive immunity and to what extent.[32] We defer to the Legislature, as the peopleâs representative body, so that it may âprotect its policymaking function,â ârespond to changing conditions,â and ârevise existing agreements if doing so would benefit the public.â[33] To ensure âthis legislative control is not lightly disturbed,â we look to statutory law to determine if the Legislature has clearly and unambiguously waived governmental immunity.[34] In 2005, the Legislature waived immunity for certain breach-of-contract suits,[35] âalter[ing] decades of one-sided bargains, in which local governments were wholly immune from breaches of their obligations.â[36] Section 271.152 delineates when immunity is waived: A local governmental entity that is authorized by statute or the constitution to enter into a contract and that enters into a contract subject to this subchapter waives sovereign immunity to suit for the purpose of adjudicating a claim for breach of the contract, subject to the terms and conditions of this subchapter.[37] The partiesâ dispute turns on whether SAWS entered into âa contract subject to this subchapter,â which the Act defines to include âa written contract stating the essential terms of the agreement for providing goods or services to the local governmental entity that is properly executed on behalf of the local governmental entity.â[38] Three components of this definition are at issue in this appeal: whether (1) the Contract constitutes âa written contractâ (2) that states âthe essential terms of the agreementâ (3) âfor providing . . . servicesâ to SAWS.[39] 1. âa written contractâ We first consider the threshold requirement to establish a waiver of governmental immunity under the Act: the existence of a written contract.[40] To constitute âa written contract,â an agreement must be reduced to writing and satisfy the basic requirements of contract formation,[41] although it need not âultimately be enforceable to clear the jurisdictional hurdle.â[42] If the formation requirements are not satisfied, there is no contract for a governmental entity to âenter[],â regardless of any written instrument purporting to be a contract.[43] Generally, âthe formation of a contract requires a bargain in which there is a manifestation of mutual assent to the exchange and a consideration.â[44] Expanding on the court of appealsâ holding that the Developer could have unilaterally decided not to complete any provisions of the Contract,[45] SAWS challenges whether the Contract satisfies these formation requirements. According to SAWS, because the Developerâs performance of developing the tract and connecting to SAWSâs sewer system was optional, the Contract constitutes only a âunilateral option agreement that [the Developer] had the opportunity to accept by performance within ten years,â and a unilateral contract âwould not form until [the Developer] fully performed, which never occurred.â[46] The Developer disputes this characterization, arguing that the Contract is bilateral (with some unilateral aspects) but even if not, the Developerâs actual participation in the Southside project formed a contract. Typically, parties enter into a written contract through signing a document,[47] and subsequent performanceâlike participation in the Southside projectâwould not be relevant to whether a contract is subject to the Act.[48] But for unilateral contracts, considering subsequent performance may be necessary to determine whether a contract was formed and when the governmental entity âenter[ed] intoâ it.[49] In City of Houston v. Williams, for example, we considered whether city ordinances that promised firefighters overtime and termination pay in exchange for their services and ârequired acceptance by performanceâ constituted a contract subject to the Act.[50] We noted that âa unilateral employment contract is created when an employer promises an employee certain benefits in exchange for the employeeâs performance, and the employee performs.â[51] Because the firefighters accepted the cityâs promised terms through their subsequent performance, we held that the ordinances âconstitute a unilateral contract that became effective and enforceable as to these retired Firefighters who have completed the requested performance.â[52] Here, however, we need not decide whether the Contract was a unilateral option agreement or a bilateral contract at the time the parties signed it. The Developer proffered evidence that it decided to participate in and performed on the Southside project, thereby showing that a contract would have formed through either acceptance or actual performance of the option to participate. In the Contract, SAWS promised the Developer an option to participate in the Southside project. If it âdecide[d]â to participate â within 2 weeks of bid opening,â the Developer would be prohibited from interrupting the project schedule, obligated to pay its share of the oversizing costs âprior to contract award,â and responsible for its cost share of any change orders. In return, the Developer would be eligible for collection credits that it could use to satisfy a portion, or all, of its collection impact fees. Obligations also extended beyond the Contractâs term whether or not the Southside project was completed: SAWS would continue to accept wastewater flows, recognize a right to remaining unused capacity, and apply the Developerâs impact-fee credits.[53] Both sides exchanged promises regarding their respective obligations related to the option, and SAWS would âenter[] intoâ that contract on its formation through the Developerâs acceptance of the option.[54] Alternatively, SAWSâs unilateral-contract theory leads to a similar result. If the Developer performed by participating in and funding the Southside project, SAWSâs putative unilateral offer would become a unilateral contract.[55] Even if the project constituted only partial performance of the Contract as a whole, the Contract imposes legal obligations on SAWS based on the Developerâs performance on the Southside project, including that the Developer would be eligible for collection credits.[56] In the lower courts, it was undisputed that the Developer decided to participate in and timely completed the Southside project.[57] The Developer also attached to its response to SAWSâs plea to the jurisdiction an email exchange between SAWS and an engineer stating that the oversized design for the Southside project âwas chosen, funded by the Developer & constructed.â Under our standard for reviewing plea-to-the-jurisdiction evidence that implicates the merits of the case, this evidence satisfies the initial inquiry of whether SAWS entered into a written contract.[58] We reiterate that this jurisdictional hurdle does not require proof of the contractâs ultimate enforceability; rather, it is sufficient for a plaintiff to raise a fact issue on the formation of the written contract.[59] Clearing this initial hurdle is merely an opening move for a plaintiff to have its day in court, a move that does not require rigorous proof, the marshaling of all evidence, or conclusively establishing oneâs claim.[60] Because the Developer has met this threshold burden, we turn now to âthe terms of the written agreementâââthe substance that determines whether immunity is waived.â[61] 2. âstating the essential terms of the agreementâ For a written contract to be âsubject toâ the Act, it must state âthe essential terms of the agreement.â[62] The Developer primarily relies on the written terms related to its option to participate in the Southside project. SAWS does not dispute the existence of any âessentialâ termsâ the âbasic obligationsâ to participate âare clearly outlinedâ in the Contract.[63] Rather, citing Lubbock County, SAWS argues, and the court of appeals held, that there was no âagreementâ to participate for two primary reasons: (1) SAWS had no contractual right to the Developerâs participation at the time the parties signed the Contract; and (2) the Contract contained no terms requiring SAWS to pay the Developer.[64] In considering each of these arguments, we clarify Lubbock Countyâs scope and conclude that neither reason prevails here. In Lubbock County, we considered whether a lessee agreed to provide marina-operation services to a water district when a lease provision required the districtâs premises âto be used only as a Lake marina.â[65] Although we noted that both parties âmay have contemplated that [the lessee] would operate a marina,â we recognized the distinction between restricting the use of property to a specific purpose, which imports no obligation to use the premises, and requiring the use of property for a specific purpose.[66] In concluding that the use-restriction provision was not an agreement to provide services, we explained, âWhen a party has no right under a contract to receive services, the mere fact that it may receive services as a result of the contract is insufficient to invoke [the Act's] waiver of immunity.â[67] The court of appeals construed Lubbock County as requiring an enforceable contractual right to the provision of services in the first instance.[68] In the usual case, a contract subject to the Act would provide this contractual right. But Lubbock County left open the possibility that something more than the âmere factâ that services may be received could trigger the Actâs waiver, even if there was no enforceable contractual right in the first instance.[69] Our approach was faithful to the statutory language: the Act does not require a âwritten contract that is an agreement for providing . . . servicesâ[70] but a contract that states the essential terms of an agreement for providing services.[71] An âagreementâ is âa manifestation of mutual assent.â[72] Although mere contemplation of services being performed, as in Lubbock County, is not âa manifestation of mutual assentâ to service terms,[73] an âagreementâ does not necessarily create an enforceable contractual right to those services at the time those terms are stated and in the first instance.[74] Our case law confirms this. In Williams, the city ordinances stated the terms for firefighters to provide services, but the city did not have an enforceable contractual right to their services. And after the terms were mutually assented toâthrough the firefightersâ performanceâand a unilateral contract had been formed, the city had already received the services.[75] The contract was subject to the Act even though the city never had an enforceable contractual right to receive those services. Nor must a contractual right necessarily be enforceable in the first instance. Consider, for example, a contract that satisfies formation requirements but predicates service obligations on certain conditions precedent. âConditions precedent to an obligation to perform are those acts or events, which occur subsequently to the making of a contract, that must occur before there is a right to immediate performance and before there is a breach of contractual duty.â[76] Such a contract would state terms for providing services that were agreed to, even if the contractual right was not immediately enforceable. We need not spell out the precise contours of these distinctions here. As we have already explained, the acceptance of the Developerâs option to participate would create a contractual right to its participation and share of the costs. And under SAWSâs unilateral-contract theory, the Developerâs actual performance would have provided the necessary manifestation of mutual assent, as the firefightersâ performance in Williams did. One way or another, the record indicates that the parties agreed to the terms of the Developerâs participation in the Southside project at the relevant time of contract formation. We next consider SAWSâs argument regarding the absence of a payment provision. In Lubbock County, we found further support for our conclusion that the parties did not mutually assent to the provision of services because the lease contained no terms in which the district agreed to pay âany amountâ for the lessee to provide marina-operation services. [77] We also noted that the Act limited recoverable damages to ââthe balance due and owed by the local governmental entity under the contract,â plus attorneyâs fees and interest.â[78] Construing the Actâs immunity waiver in light of this damages limitation, we recognized that the âwaiver will typically apply only to contracts in which the governmental entity agrees to payâ for the services.[79] But the absence of a payment provision is not dispositive. We held that it âmay indicate that the claimant did not in fact agree to provideâ the services.[80] And we also noted that a party may agree to provide services âin exchange for something other than payment.â[81] Moreover, since Lubbock County, we have (1) recognized that the Actâs damages limitation did not preclude specific performance as a remedy[82] and (2) broadly interpreted the statutory phrase âthe balance due and owedâ to mean âthe amount of damages for breach of contract payable and unpaid,â even if the amount is not âstated in,â âexpressly provided for in,â or even âascertainable fromâ the contract.[83] Lubbock County and its progeny instruct that the absence of an express money-payment provision, standing alone, must not be given too much weight in determining whether contracting parties agreed to service terms, so long as the service terms are âsufficiently definite to âenable a court to understand the partiesâ obligations,â and to give âan appropriate remedyâ if they are breached.â[84] In marked contrast to Lubbock County, there is no dispute here that the parties agreed to and expressly chose a method of exchangeâ collection creditsâfor the Developerâs participation.[85] These collection credits could be used to satisfy the assessed collection impact fee, which the Contract estimates would cost $549,000 for 1,500 EDUs. SAWS nevertheless alleges that these credits âdo not provide financial valueâ because credits and impact fees are a functionally equivalent and interchangeable means of ensuring a developer of new property bears the cost of the necessary infrastructure to serve that development.[86] In the abstract and from a regulatory perspective, SAWS may be correct. In practice and from a developerâs perspective, however, the credits and fees are not equivalent. By agreeing to be eligible for collection credits that could then be used to satisfy impact fees, the Developer exercised greater control over when it would expend resources to fund off-site infrastructure while receiving a guarantee that additional off-site infrastructure construction would not be necessary.[87] The Contract also expressly contemplates that the collection credits could exceed the assessed collection impact fees.[88] And under SAWSâs regulations, these credits would not expire and are transferrable âto another development owned by the same developer.â[89] Given this, we disagree that the credits provide the Developer with no value. In sum, the Contract states the essential terms for the Developer to participate in the Southside project, the parties manifested mutual assent to those terms through the Developerâs participation, and the parties agreed that the Developer would be eligible for collection credits in exchange for its participation. 3. âagreement for providing . . . servicesâ to SAWS Although the Contract states the essential terms of an agreement for the Developer to participate in the Southside project, it would not be subject to the Act unless the agreement was for providing services to SAWS.[90] We have taken a broad view of what âservicesâ encompasses, holding that it âincludes generally any act performed for the benefit of another.â[91] The only limitation our case law imposes is that the services must provide more than a mere ââindirect, attenuatedâ benefit.â[92] In our analogous decision in Kirby Lake Development, Ltd. v. Clear Lake City Water Authority, we addressed whether certain agreements for developers to construct water and sewer facilities according to a water authorityâs specifications were for providing services to the authority.[93] The agreements also stipulated that the developers would lease the facilities to the authority free of charge until the authorityâif it received voter-approved bond fundsâpurchased them by partially reimbursing construction costs.[94] In considering those services, we cited with approval a court of appealsâ decision that an âagreement to hire third parties to construct the Facilities and to build the streets, roads, and bridges is . . . sufficient to constitute the provision of services to the authority.â[95] Drawing on this holding, we concluded that the agreements entailed âservices provided directly toâ the authority.[96] Similarly, the Developer here agreed to the terms to participate in and fund the construction of off-site oversized lift stations and sewer mainsâcapital improvements[97]âaccording to SAWSâs specifications. After determining the capital improvements would âbe an integral part of [SAWS]âs regional sewerage systemâ and accepting them, SAWS would own the infrastructure and generate revenue through monthly service fees in servicing the developments with this capacity.[98] If there was any unused capacity, SAWS had the contractual right âto connect wastewater flows from other developmentsâ and could use the infrastructure to service other developments and generate additional revenue, as it apparently did after the ten-year term passed. And by exchanging collection credits for participation, SAWS received the benefit of having its capital improvements financed at the time of construction without the up-front expenditure of governmental funds.[99] No doubt, the services to SAWS were not the central purpose of the Contract, which states that the Southside project was âto accommodate flows from the [Developer's] development.â But we have repeatedly emphasized that the agreement to provide services need not be the âprimary purpose,â[100] provided the benefits to the governmental entity are âsufficiently direct and concrete.â[101] Although the Kirby Lake homeownersâand not the governmental entityâwere âarguably the ultimate beneficiaries of the developersâ efforts to build water and sewer facilities,â this circumstance did not take those contracts outside the Actâs scope.[102] So too here. On this plea-to-the-jurisdiction record, when the Developer participated in the Southside project and a contract formed, the agreementâs benefits to SAWS were sufficiently direct and concrete for the Contract to fall within the Actâs scope. * * * Because the Developer adduced evidence that SAWS entered into a written contract that states the essential terms of an agreement for providing services toSAWS, the trial court correctly denied SAWSâs plea to the jurisdiction. The court of appeals erred in concluding otherwise. B. Dilatory Plea Finally, SAWS broaches the merits in this appeal, challenging whether the Developer acquired a vested right to the 1,500 EDUs. We express no opinion on this matter. A dilatory pleaâs purpose âis to defeat a cause of action without regard to whether the claims asserted have merit,â ânot to force the plaintiffs to preview their case on the merits.â[103] When an authorized local governmental entity enters into a contract subject to the Act, immunity from suit is waived âfor the purpose of adjudicating a claim for breach of the contract,â[104] but â[t]he waiver does not depend on the outcome.â[105] Here, the Developer has âplead[ed] facts with some evidentiary support that constitute a claim for which immunity is waivedâ and has shown that it is entitled, at least for now, to its day in court against SAWS.[106] III. Conclusion For these reasons, we reverse the court of appealsâ judgment and remand the case to the trial court for further proceedings consistent with this opinion. John P. Devine Justice OPINION DELIVERED: April 12, 2024