X

Thank you for sharing!

Your article was successfully shared with the contacts you provided.

MEMORANDUM AND ORDER Plaintiffs Pamela Mahoney, Michael Mahoney, Lisa Solomon, and Mitch Solomon (“Plaintiffs”) are two married couples with residences in the Wainscott hamlet of East Hampton, New York. They seek a preliminary injunction1 to halt onshore trenching for the South Fork Wind Farm and South Fork Export Cable Project (the “project”). Plaintiffs claim that the onshore digging will disrupt perfluoroalkyl and polyfluoroalkyl substances (“PFAs”) present in the groundwater, worsening the existing PFAS pollution in the wells on Plaintiffs’ properties. Defendants U.S. Department of the Interior (“DOI”), Bureau of Ocean Energy Management (“BOEM”), U.S. Department of the Army (“Army”), and U.S. Army Corps of Engineers (“Army Corps”) (together, “Defendants”) are the federal government agencies that issued the permits for the offshore portion of the project and the final environmental impact statement (“FEIS”) required by law to grant those permits. Defendant-Intervenor South Fork Wind, LLC (“SFW”) is the developer of the project. For the following reasons, Plaintiff’s motion is denied. I. FACTS SFW is the developer of a commercial wind farm off the eastern shore of Long Island. The wind farm is located in federal waters 35 miles east of Montauk Point, Long Island. To export the energy from the windmills to an existing onshore electric grid in East Hampton, trenches will be excavated to store underground cables which will transfer the energy. The onshore route for the underground electric cables will pass by properties owned by the Plaintiffs in Wainscott. Plaintiffs, whose groundwater is presently contaminated by PFAS to the extent that they do not use their onsite water wells for drinking water, allege that trenching will exacerbate PFAS contamination of the water on their properties. The permits to conduct the offshore portion of the project were issued by Defendants. For the onshore portion of the project, and specifically the trenching that Plaintiffs claim will lead to further contamination of their groundwater, the permits were issued by the New York Public Service Commission (“NYPSC”). After years of administrative proceedings, the NYPSC issued a Certificate of Environmental Compatibility and Public Need under Article VII of the Public Service Law allowing the project to move forward. These proceedings considered, among other things, the potential of the project to exacerbate PFAS contamination. The public was able to participate in the proceedings through hearings and the submission of testimony or comments. Plaintiffs participated in this process. The NYPSC found that the project would not exacerbate existing PFAS contamination, in part because as proposed, the project provided for preventative measures to ensure that groundwater flow was not materially altered. The NYPSC later denied a rehearing of the issue, holding that petitioners had not submitted sufficient evidence to demonstrate that the project’s provisions for dealing with PFAS were inadequate. Subsequently, a non-profit organization called Citizens for the Preservation of Wainscott, Inc. (“CPW”) appealed NYPSC’s decision to New York state court, asking the court to enjoin SFW from onshore trenching. The state court denied the appeal on January 26, 2022. Separately, CPW and the Plaintiffs in this action filed a petition in New York state court challenging the easement that the town of East Hampton had granted to SFW for the trenching in question. The state court denied that petition on February 17, 2022. It held that any potential migration of PFAS as a result of the project could not stem from the grant of the easement, but from the manner in which the trenching is conducted. The court also found that challenges to the manner of construction were properly considered by the NYPSC, and that any further challenges to this should have been brought in the NYPSC’s proceedings, not before the state court. On March 9, 2022, Plaintiffs brought the current action. They argue that Defendants did not conduct an adequate review of the project’s effect on PFAS contamination in the FEIS, and therefore violated the National Environmental Policy Act (“NEPA”), the Clean Water Act (“CWA”), Outer Continental Shelf Lands Act (“OCSLA”), and Administrative Procedure Act (“APA”). Plaintiffs seek preliminary injunctive relief to halt construction of the onshore export cable. II. PRELIMINARY INJUNCTION “A plaintiff seeking a preliminary injunction must establish that he is likely to succeed on the merits, that he is likely to suffer irreparable harm in the absence of preliminary relief, that the balance of equities tips in his favor, and that an injunction is in the public interest.” Winter v. Natural Resources Defense Council, Inc., 555 U.S. 7, 20 (2008). If an injunction “disrupt[s] the status quo, a party seeking one must meet a heightened legal standard by showing ‘a clear or substantial likelihood of success on the merits.’” N. Am. Soccer League, LLC v. U.S. Soccer Fed’n, Inc., 883 F.3d 32, 37 (2d Cir. 2018) (quoting N.Y. Civil Liberties Union v. N.Y.C. Transit Auth., 684 F.3d 286, 294 (2nd Cir. 2012)). “Perhaps the single most important prerequisite for the issuance of a preliminary injunction is a demonstration that if it is not granted the applicant is likely to suffer irreparable harm before a decision on the merits can be rendered.” Bell & Howell: Mamiya Co. v. Masel Supply Co. Corp., 719 F.2d 42, 45 (2d Cir. 1983). To establish irreparable harm, a movant “must demonstrate an injury that is neither remote nor speculative, but actual and imminent and that cannot be remedied by an award of monetary damages.” Shapiro v. Cadman Towers, Inc., 51 F.3d 328, 332 (2d Cir. 1995) (internal quotation omitted). III. ANALYSIS Plaintiffs argue that without a preliminary injunction they will be irreparably harmed by the likely exacerbation of preexisting PFAs contamination of the groundwater on their properties. To succeed on this prong, Plaintiffs must demonstrate that irreparable harm is not just possible, but likely. See Winter v. Natural Resources Defense Council, Inc., 555 U.S. 7, 22 (2008). Plaintiffs have failed to do so. They rely heavily on their expert John A. Conrad’s (“Conrad”) declaration which concludes that “it is likely that the trench will become a preferential pathway for PFAS movement, carrying PFAS contaminants to locations that would otherwise not be impacted […] and, more likely than not, will contaminate or further impact the Mahoney’s water supply well located on their property.” Declaration of John A. Conrad at 16-17. However, Conrad’s assertion is conclusory. He does not provide support as to why this result is “likely,” nor does he address the effect of the mitigation measures provided for in SFW’s plan, which was approved by the NYPSC. At oral argument, Plaintiffs’ counsel stated that “one problem with PFAS is that it’s difficult to remediate.” Tr. at 9.2 However, it is possible to remediate PFAS contamination. See Declaration of Kenneth Bowes at 29. Currently, the New York State Department of Environmental Conservation is undertaking remedial measures in East Hampton to address PFAS contamination in the area. See id. This likewise undercuts the Plaintiffs’ claims of irreparable harm. Also, assuming that the project risks spreading PFAS, counsel for the Defendants argues that “[t]here are measures in place” to ensure that this does not occur. Tr. at 12. These measures were conditions on the issuance of the project’s permits by the NYPSC and were later incorporated by reference into the FEIS by the federal agencies. Tr. 12. In addition, PFAS already exists on Plaintiffs’ properties. Finally, that Plaintiffs failed to seek injunctive relief in this court until months after the FEIS was issued and until after they received unfavorable decisions in state court further “undercuts the sense of urgency that ordinarily accompanies a motion for preliminary relief and suggests that there is, in fact, no irreparable injury.” Tough Traveler, Ltd. v. Outbound Prod., 60 F.3d 964, 968 (2d Cir. 1995) (quoting Citibank, N.A. v. Citytrust, 756 F.2d 273, 277 (2nd Cir. 1985)). CONCLUSION The Court finds that Plaintiff failed to establish irreparable harm — “the single most important prerequisite for the issuance of a preliminary injunction,” Masel Supply Co. Corp., 719 F.2d at 45 — and so denies Plaintiff’s motion. SO ORDERED. Dated: April 12, 2022

 
Reprints & Licensing
Mentioned in a Law.com story?

License our industry-leading legal content to extend your thought leadership and build your brand.

More From ALM

With this subscription you will receive unlimited access to high quality, online, on-demand premium content from well-respected faculty in the legal industry. This is perfect for attorneys licensed in multiple jurisdictions or for attorneys that have fulfilled their CLE requirement but need to access resourceful information for their practice areas.
View Now
Our Team Account subscription service is for legal teams of four or more attorneys. Each attorney is granted unlimited access to high quality, on-demand premium content from well-respected faculty in the legal industry along with administrative access to easily manage CLE for the entire team.
View Now
Gain access to some of the most knowledgeable and experienced attorneys with our 2 bundle options! Our Compliance bundles are curated by CLE Counselors and include current legal topics and challenges within the industry. Our second option allows you to build your bundle and strategically select the content that pertains to your needs. Both options are priced the same.
View Now
September 05, 2024
New York, NY

The New York Law Journal honors attorneys and judges who have made a remarkable difference in the legal profession in New York.


Learn More
April 25, 2024
Dubai

Law firms & in-house legal departments with a presence in the middle east celebrate outstanding achievement within the profession.


Learn More
April 29, 2024 - May 01, 2024
Aurora, CO

The premier educational and networking event for employee benefits brokers and agents.


Learn More

A large and well-established Tampa company is seeking a contracts administrator to support the company's in-house attorney and manage a wide...


Apply Now ›

We are seeking an attorney to join our commercial finance practice in either our Stamford, Hartford or New Haven offices. Candidates should ...


Apply Now ›

We are seeking an attorney to join our corporate and transactional practice. Candidates should have a minimum of 8 years of general corporat...


Apply Now ›
04/15/2024
Connecticut Law Tribune

MELICK & PORTER, LLP PROMOTES CONNECTICUT PARTNERS HOLLY ROGERS, STEVEN BANKS, and ALEXANDER AHRENS


View Announcement ›
04/11/2024
New Jersey Law Journal

Professional Announcement


View Announcement ›
04/08/2024
Daily Report

Daily Report 1/2 Page Professional Announcement 60 Days


View Announcement ›